Paul Tung

PAST EXPERIENCE

  • 41 years in construction with Contractors & LTA
  • Experience in
    – Deputy Director (24 years)
    – Senior Manager (8 years)
    – Senior Quantity Surveyor (10 years)
  • Qualifications
    – Bachelor of Science Bsc (Building) from the National University of Singapore (NUS)  -> 1979
    – Professional Associate of the Royal Institution of Chartered Surveyors (RICS) -> 1985
    – Member of Royal Institution of Chartered Surveyor
  • Past Companies
    – LTA
    – Lim Kah Ngam Pte Ltd
    – Active Construction
    – L&M International
    – Econ International/Piling Piling

PAST PROJECTS

Thomson-East Coast Line (6 Stations & Tunnels)     $1.8 Billion

T216 Construction of Stevens Station and Tunnels $441milion
T217 Construction of Napier Station and Tunnels $189million
T218 Construction of Orchard Boulevard Station $143million
T219 Construction of Orchard Station and Tunnels $499million
T220 Construction of Great World Station and Tunnels $316million
T221 Construction of Havelock Station $211million

Downtown Line (6 Stations & Tunnels)

  • Expo, Upper Changi, Tampines East, Tampines Central, Tampines West & Bedok Reservoir station

Circle Line (5 Stations & Tunnels)

  • Serangoon, Bukit Brown, Caldecott, Botanic Gardens & Farrer Road stations

North East Line (2 Stations & Tunnels)

  • Little India & Farrer Park Stations

North-West Line (3 Stations & Viaducts)             Oct 1985 – May 1989

  • Changi Depot, Simei, Tampines & Pasir Ris Stations

CONTRACT CLAIMS

Mr Tung is seasoned in Contractual Claims.

Below are some examples of his successful claims.

  • Adverse Ground Condition Encounted at Bukit Timah Hill
    – Claim of compensation of $500,000 and Extension of Time (EOT) of 30 days.
    – Successfully win a claim of $450,000.
  • Encountering of Unforeseen Obstruction during Bored tunning works resulting in standby of TBM
    – Claim of compensation of $5.5 million and Extension of Time (EOT) for 150 days.
    – Successfully win a claim of $4 million and EOT of 157 days.
  • Revised Constructions scheme of Underpass to Entrance
    – Claim of compensation of $15 million
    – Successfully win a claim of $9 million